Wednesday, October 29, 2014
Tuesday, October 28, 2014
attic and porches
After finishing the walls we installed the 18K9 open web joist for the attic and porches
steel columns and C channel in place
Decking attached
second floor nailer in place, just waiting on roof trusses.
Next step will be waterproofing the window/door bucks and installing windows and siding...still a long was to go.
steel columns and C channel in place
Decking attached
second floor nailer in place, just waiting on roof trusses.
Next step will be waterproofing the window/door bucks and installing windows and siding...still a long was to go.
2nd floor walls
More ICF fun...
2nd floor walls ready for 1st pour
2nd floor walls poured
2nd floor wall pony wall ready for concrete
Walls finished!!!
2nd floor walls ready for 1st pour
2nd floor walls poured
2nd floor wall pony wall ready for concrete
1st floor walls and Hambro
So we finished the first floor slab and started on the first floor walls
first floor walls braced and ready for the pour
Pour complete......learned a whole lot that day.
We chose the Hambro composite steel joist concrete floor system for the house.
first floor walls braced and ready for the pour
Pour complete......learned a whole lot that day.
We chose the Hambro composite steel joist concrete floor system for the house.
Monday, October 27, 2014
Getting started
We started our ICF house a few months ago, I've been pretty busy so I'm finally getting around to put up a blog on it. I'll update from time to time.
Sub-piling complete
Grade beam ready for concrete
Grade beams poured